Deanrock Housing Development, Cork
Client
Cork County Council
Project Duration
17 months
Design Team
Cork City Council,
Architects Department
Downes Associates Ltd.
Matt O’Mahoney & Associates
Harris Coyle Breen Chartered QS
Project Description
The Deanrock Housing project involved the construction of 65 No. residential housing units and a ground floor community facility with associated site works.
The project commenced in April 2018 and the estimated works took 21 months to complete. This project was completed in phases. Phase 1, Blocks B/A & F of this project were completed in July, 2019. Phase 2 (C, L, G, E) completed by 8th November 2019 with Phase 3 (D, H, J, K) March 2020.