MSD Truegrid, Dunboyne
Client
MSD Dunboyne Biologics
Project Duration
18 months
Design Team
Architect: MSD
Engineer: Jacobs Engineering
Project Description
As the main contractor, we successfully completed various works across multiple areas. In the Warehouse Area, we reconfigured the existing freezer room and carried out associated works. In the Cell Culture Room (LAC Level 1), we undertook the reconfiguration of the existing room and its associated works. For the Microbiology Lab Area, we ensured the protection of the existing area and made all necessary restorations upon completion. Similarly, in the Cell Biology Area (LAC Level 1), we protected the existing area and restored it after the work was completed. The Sample Control Room (LAC Level 1) saw the protection of the existing area and a reconfiguration of its entrance. In the Analytical Lab (LAC Level 2), we protected the existing area and made good after the work was finished. Additionally, we protected the Clean Room Areas and restored them upon completion of the works.