Element Six, Shannon, Co. Clare
Client
Element 6 Ireland
Project Duration
16 Weeks
Design Team
Barry Sheppard & Associates
Garland Consultancy
Don O’Malley & Partners
Garland Safety Management
Project Description
The works involved the fit-out of Bay 37F1 at Element Six, Shannon Airport, Shannon, Co. Clare including the construction and fit-out of a number of pre-synthesis clean rooms in an existing industrial unit; the construction of services interstitial level over the clean rooms supported by steel beams; the construction of external fire escape stairs and M&E installations within Bay 37F1 to serve the new pre-synthesis clean rooms including the installation of a number of air handling units.