Scoil Phóil Naofa, Limerick
Client
Board Of Management
Project Duration
16 Months
Design Team
Healy Partners
Rogerson Reddan
Garland Consultancy
Matt O’Mahony & Associates
Project Description
The works comprised of the demolition of an existing single storey central block and replacement with a new two-storey 8 classroom block with GP hall (with a total gross floor area of c 2,311m2; the refurbishment of 2 No. existing two-storey classroom blocks (total gross floor area of 1,387m2) and all ancillary accommodation.
The site development works comprised of the construction of a new 2-way access road off St. Nessan’s Road roundabout, with provision for new hard surface playing areas and a dedicated staff carpark on the lower field, new set down areas and visitor parking off Springfield Drive entrance and all associated landscaping, services including the boundary works.